- To answer a question: choose one of the four options, then press Save & Next. To change an answer, select a different option and save again. To remove it, press Clear.
- Your answer is saved only when you press Save & Next or Mark for Review & Next. If you jump to another question from the palette without saving, the answer to the question you were on is not kept. This is how the real exam behaves.
- Sections appear on the bar above the question. You may move between sections at any time, and after the last question of a section you are taken to the first question of the next one.
- Only questions that are saved, or marked for review after answering, are evaluated.
Quant – Time & Work – Set 5
Read the following instructions carefully
- The test contains 10 questions.
- Each question has 4 options, of which only one is correct.
- You have to finish the test in 8 minutes.
- You are awarded 1 mark for each correct answer, and 0.25 marks are deducted for each wrong answer.
- There is no negative marking for questions you do not attempt.
- You may pause the test at any time and resume where you left off.
- Your marks, the correct answers and an explanation for every question are shown as soon as you submit.
- You can take this test as many times as you like. A fresh set is drawn each time you reload the page.
Test paused
The clock has stopped. Your answers are safe.
Question Paper
Your paper has been submitted
Your answers are saved on our server. Marks are not shown here — results are published on our Telegram channel on .
Review this set's questions and answers (opens after you submit the test)
This free practice set from AndamanJobs has 10 questions to be solved in 8 minutes. Every question is listed below with four options. Open Show answer and explanation under a question to see the correct option and why it is correct. Try the timed test above first, then use this list to revise the questions you got wrong.
- A man, a woman and a boy together finish a piece of work in 6 days. If a man and a woman can do the work in 10 and 24 days respectively. The days taken by a boy to finish the work is :
- A. 35 days
- B. 40 days
- C. 45 days
- D. 30 days
Show answer and explanation
Answer: B. 40 days
Boy's rate = 1/6 - 1/10 - 1/24 = (20 - 12 - 5)/120 = 1/40. The boy takes 40 days.
- 3 men and 7 women can do a job in 5 days, while 4 men and 6 women can do it in 4 days. The number of days required for a group of 10 women working together, at the same rate as before, to finish the same job is :
- A. 20 days
- B. 36 days
- C. 40 days
- D. 30 days
Show answer and explanation
Answer: A. 20 days
(3M + 7W) × 5 = (4M + 6W) × 4 gives M = 11W. Total work = 5 × (33 + 7) = 200 woman-days. 10 women take 200/10 = 20 days.
- A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 3/5 of the work. The number of men he can withdraw so that the work is still finished in time is:
- A. 40
- B. 30
- C. 45
- D. 35
Show answer and explanation
Answer: B. 30
110 men × 48 days = 5,280 man-days did 3/5 of the work, so the whole job is 8,800. Remaining 3,520 in 44 days needs 80 men. Men to withdraw = 110 - 80 = 30.
- A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now so that the work finishes in time?
- A. 56
- B. 40
- C. 48
- D. 50
Show answer and explanation
Answer: A. 56
120 × 64 = 7,680 man-days did 2/3 of the work, so the whole job is 11,520. Remaining 3,840 in 60 days needs 64 men. Discharge 120 - 64 = 56.
- A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid Rs.960 for the whole work. How much money A gets?
- A. Rs. 320
- B. Rs. 400
- C. Rs. 240
- D. Rs. 480
Show answer and explanation
Answer: B. Rs. 400
Work = 60 units; A does 5 and B does 4 a day. All three do 12 a day, so C does 3. A's share = 5/12 × 960 = Rs 400.
- Three persons undertake to complete a piece of work for Rs.1200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days. They complete the work with the help of a fourth person in 3 days. What does the fourth person get ?
- A. Rs. 225
- B. Rs. 250
- C. Rs. 200
- D. Rs. 180
Show answer and explanation
Answer: A. Rs. 225
Work = 48 units; the three do 6, 4, 3 = 13 a day. All four do 48/3 = 16 a day, so the fourth does 3. Share = 3/16 × 1,200 = Rs 225.
- A skilled, a half-skilled and an unskilled labourer work for 7, 8 and 10 days respectively and together get Rs 369. If the ratio of their daily work is 1/3 : 1/4 : 1/6, how much does the skilled labourer get (in Rs)?
- A. 102.50
- B. 164
- C. 143.50
- D. 201.50
Show answer and explanation
Answer: C. 143.50
Daily work ratio 1/3 : 1/4 : 1/6 = 4 : 3 : 2. Pay ratio = 4 × 7 : 3 × 8 : 2 × 10 = 28 : 24 : 20. Skilled gets 28/72 × 369 = Rs 143.50.
- Three men A, B and C working together can do a job in 6 hours less time than A alone, in 1 hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in :
- A. 1/3 hour
- B. 2/3 hour
- C. 3/2 hours
- D. 4/3 hours
Show answer and explanation
Answer: D. 4/3 hours
Let all three take t hours: A = t + 6, B = t + 1, C = 2t. 1/(t+6) + 1/(t+1) = 1/(2t) gives 3t² + 7t - 6 = 0, so t = 2/3. A = 20/3 and B = 5/3, so A + B do 3/20 + 3/5 = 3/4 an hour. Time = 4/3 hour.
- A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is :
- A. 90
- B. 100
- C. 95
- D. 96
Show answer and explanation
Answer: D. 96
A takes 3 times as long as B + C, so A does 1/4 of the total rate. Total rate = 1/24, so A = 1/96. A takes 96 days.
- 16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will they take to complete the remaining work ?
- A. 10
- B. 8
- C. 6
- D. 4
Show answer and explanation
Answer: C. 6
16 women × 12 = 192 woman-days = 12 men × 8 = 96 man-days, so 1 man = 2 women. 16 men = 32 women work 3 days = 96. Left 96. Now 6 men + 4 women = 16 women, so 96/16 = 6 days.