One notification can change your whole year. Check daily.Every government job starts with a single application.Small islands, big opportunities.Prepare today — the last date will not wait for you.Your next job may be published tomorrow morning.

Quant – Time & Work – Set 1

General Instructions

  1. The clock is set at the server. The countdown timer at the top of the screen shows the time remaining. When it reaches zero the test ends by itself — you do not have to submit.
  2. The Question Palette shows the status of every question using these symbols:
    • You have not visited the question yet.
    • You have not answered the question.
    • You have answered the question.
    • You have NOT answered, but have marked it for review.
    • You have answered and also marked it for review.
    Marking a question for review only means you want to look at it again. An answered question that is marked for review is still counted in the evaluation.
  3. To answer a question: choose one of the four options, then press Save & Next. To change an answer, select a different option and save again. To remove it, press Clear.
  4. Your answer is saved only when you press Save & Next or Mark for Review & Next. If you jump to another question from the palette without saving, the answer to the question you were on is not kept. This is how the real exam behaves.
  5. Sections appear on the bar above the question. You may move between sections at any time, and after the last question of a section you are taken to the first question of the next one.
  6. Only questions that are saved, or marked for review after answering, are evaluated.
Review this set's questions and answers (opens after you submit the test)

This free practice set from AndamanJobs has 10 questions to be solved in 8 minutes. Every question is listed below with four options. Open Show answer and explanation under a question to see the correct option and why it is correct. Try the timed test above first, then use this list to revise the questions you got wrong.

  1. A, B and C can complete a work in 10,12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left work 2 days after A left. In how many days was the work completed ?
    • A. 5 days
    • B. 4 days
    • C. 7 days
    • D. 8 days
    Show answer and explanation

    Answer: C. 7 days

    Let the work be 60 units. A, B, C do 6, 5, 4 units a day. If it ends on day T, all three work T - 5 days, then B and C work 2 days and C works the last 3 days. 15(T - 5) + 9 × 2 + 4 × 3 = 60, so T = 7 days.

  2. If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days ?
    • A. 260
    • B. 520
    • C. 280
    • D. 240
    Show answer and explanation

    Answer: A. 260

    10 men = 20 boys, so 1 man = 2 boys. 8 men + 4 boys = 10 men. 10 men make 260 mats in 20 days, so the answer is 260.

  3. A particular job can be completed by a team of 10 men in 12 days, The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?
    • A. 9 days
    • B. 18 days
    • C. 6 days
    • D. 4 days
    Show answer and explanation

    Answer: D. 4 days

    10 men do 1/12 a day and 10 women do 1/6 a day. Together 1/12 + 1/6 = 1/4 a day, so 4 days.

  4. The average wage of 500 workers was found to be ₹200. Later on , it was discovered that the wages of two workers were misread as 180 and 20 instead of 80 and 220. The correct average wage is :
    • A. Rs. 200.20
    • B. Rs. 200.50
    • C. Rs. 201.00
    • D. Rs. 200.10
    Show answer and explanation

    Answer: A. Rs. 200.20

    The total wage changes by (80 + 220) - (180 + 20) = +100. Average rises by 100/500 = 0.20, so the correct average is Rs 200.20.

  5. A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ?
    • A. 100
    • B. 75
    • C. 60
    • D. None of these
    Show answer and explanation

    Answer: B. 75

    24 days × 25 men = 600 man-days gave 1/3 of the road, so the whole road needs 1,800. Remaining 1,200 man-days must be done in 40 - 4 - 24 = 12 days, which needs 100 men. Extra men = 100 - 25 = 75.

  6. A can finish a work in 18 days and B can do the same work in half the time taken by A. Then working together, what part of the same work can they finish in a day ?
    • A. 1/6
    • B. 2/7
    • C. 2/5
    • D. 1/9
    Show answer and explanation

    Answer: A. 1/6

    A does 1/18 a day and B (half the time, 9 days) does 1/9 a day. Together 1/18 + 2/18 = 3/18 = 1/6 of the work a day.

  7. A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A left after sometime and B completed the remaining work in 17 days. After how many days did A leave ?
    • A. 8 days
    • B. 9 days
    • C. 7 days
    • D. 14 days
    Show answer and explanation

    Answer: A. 8 days

    Work = 140 units; A does 5 and B does 4 a day. B alone did 17 × 4 = 68, so together they did 72 units at 9 a day = 8 days. A left after 8 days.

  8. If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m ?
    • A. 10
    • B. 18
    • C. 28
    • D. 30
    Show answer and explanation

    Answer: D. 30

    Man-days per metre = 72 × 21 / 280 = 5.4. For 100 m we need 540 man-days; in 18 days that is 540/18 = 30 men.

  9. A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do the work in :
    • A. 30 days
    • B. 20 days
    • C. 15 days
    • D. 25 days
    Show answer and explanation

    Answer: D. 25 days

    A = B + C in rate, and A + B = 1/10, C = 1/50. So 2B + 1/50 = 1/10, giving B = 1/25. B alone takes 25 days.

  10. A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in :
    • A. 15 days
    • B. 8 days
    • C. 12 days
    • D. 10 days
    Show answer and explanation

    Answer: C. 12 days

    Work = 30 units; A does 2 and B does 3 a day. In 2 days they do 10 units. Remaining 20 at 2 a day = 10 days. Total = 2 + 10 = 12 days.